adplus-dvertising

Welcome to the Project Planning and Control MCQs Page

Dive deep into the fascinating world of Project Planning and Control with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Project Planning and Control, a crucial aspect of Software Engineering. In this section, you will encounter a diverse range of MCQs that cover various aspects of Project Planning and Control, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Software Engineering.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Project Planning and Control. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Software Engineering.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Project Planning and Control. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Project Planning and Control MCQs | Page 10 of 11

Discuss
Answer: (c).By taking the latest finishing time of the all the predecessor nodes Explanation:The earliest possible starting time of an activity is computed by taking the latest finishing time of the all the predecessor nodes.
Discuss
Answer: (b).The earliest finishing time of the end node Explanation:The earliest possible finishing time of the whole project is the earliest finishing time of the end node.
Discuss
Answer: (c).A path with no slack time Explanation:A critical path in PERT technique is a path with no slack time.
Discuss
Answer: (b).To synchronize interrelated activities Explanation:Dummy activities in PERT technique are used to synchronize interrelated activities.
Discuss
Answer: (a).The earliest possible starting time Explanation:The Si in the ordered pair (Si, Fi) represents the earliest possible starting time for an activity in the PERT technique.
Discuss
Answer: (b).The earliest possible finishing time Explanation:The Fi in the ordered pair (Si, Fi) represents the earliest possible finishing time for an activity in the PERT technique.
Discuss
Answer: (a).To depict the time span of each activity in the project Explanation:A Gantt chart in the PERT technique is used to visually represent the time span of each activity in the project. It shows the duration of each activity and their corresponding starting and finishing times.
Discuss
Answer: (a).In an activity-on-node network, activities are depicted as arrows and the nodes represent completion of milestone events, while in an activity-on-arrow network, the arrows represent activities and the nodes denote precedence relations between activities. Explanation:An activity-on-node network is a type of network diagram where the activities are depicted as nodes, while the arrows denote the precedence relations between activities. In contrast, an activity-on-arrow network, the arrows represent activities and the nodes denote completion of milestone events.
Discuss
Answer: (c).To make sure that certain activities are not started until certain other activities have been completed Explanation:Dummy activities in an activity-on-arrow network are used to ensure that certain activities are not started until certain other activities have been completed.
Discuss
Answer: (b).To visualize the result of network analysis Explanation:The Gantt charts are used as a means to visualize the result of network analysis, and do not carry information on dependencies between activities.
Page 10 of 11

Suggested Topics

Are you eager to expand your knowledge beyond Software Engineering? We've curated a selection of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!