1. | RAD Software process model stands for _____ . |
a. | Rapid Application Development. |
b. | Relative Application Development. |
c. | Rapid Application Design. |
d. | Recent Application Development. |
View Answer Report Discuss Too Difficult! |
Answer: (a).Rapid Application Development.
|
2. | What is the simplest model of software development paradigm? |
a. | Spiral model |
b. | Big Bang model |
c. | V-model |
d. | Waterfall model |
View Answer Report Discuss Too Difficult! |
Answer: (d).Waterfall model
|
3. | The architectural model is derived from which of these sources? A) Information about the application domain for the software to be built; B) Specific requirements model elements such as data flow diagrams or analysis classes, their relationships and collaborations for the problem at hand; C) The availability of architectural styles and patterns. |
a. | Both A & B |
b. | Both B & C |
c. | Both A & C |
d. | All mentioned above |
View Answer Report Discuss Too Difficult! |
Answer: (d).All mentioned above
|
4. | Which model is also known as Verification and validation model? |
a. | Waterfall model |
b. | Big Bang model |
c. | V-model |
d. | Spiral model |
View Answer Report Discuss Too Difficult! |
Answer: (c).V-model
|
5. | Which model is not suitable for large software projects but good one for learning and experimenting? |
a. | Big Bang model |
b. | Spiral model |
c. | Iterative model |
d. | Waterfall model |
View Answer Report Discuss Too Difficult! |
Answer: (a).Big Bang model
|
6. | Which model is also called as the classic life cycle or the Waterfall model? |
a. | Iterative Development |
b. | Linear Sequential Development |
c. | RAD Model |
d. | Incremental Development |
View Answer Report Discuss Too Difficult! |
Answer: (b).Linear Sequential Development
|
7. | What is the average effective global activity rate in an evolving E-type system is invariant over the lifetime of the product? |
a. | Self-regulation |
b. | Reducing quality |
c. | Feedback systems |
d. | Organizational stability |
View Answer Report Discuss Too Difficult! |
Answer: (d).Organizational stability
|
8. | Build & Fix Model is suitable for programming exercises of ___________ LOC (Line of Code). |
a. | 100-200 |
b. | 200-400 |
c. | 400-1000 |
d. | above 1000 |
View Answer Report Discuss Too Difficult! |
Answer: (a).100-200
|
9. | Which one of the following models is not suitable for accommodating any change? |
a. | Build & Fix Model |
b. | Prototyping Model |
c. | RAD Model |
d. | Waterfall Model |
View Answer Report Discuss Too Difficult! |
Answer: (d).Waterfall Model
|
10. | Which is not one of the types of prototype of Prototyping Model? |
a. | Horizontal Prototype |
b. | Vertical Prototype |
c. | Diagonal Prototype |
d. | Domain Prototype |
View Answer Report Discuss Too Difficult! |
Answer: (c).Diagonal Prototype
|