Question
a.
To represent the earliest possible starting and finishing times for each activity
b.
To show the critical path of activities
c.
To make sure that certain activities are not started until certain other activities have been completed
d.
To show the slack times of activities
Posted under Software Engineering
Engage with the Community - Add Your Comment
Confused About the Answer? Ask for Details Here.
Know the Explanation? Add it Here.
Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?
Similar Questions
Discover Related MCQs
Q. What is the purpose of a Gantt chart in project management?
View solution
Q. How can project expenditures be planned using a Gantt chart?
View solution
Q. What is used to determine cumulative effort and expenditure during a project?
View solution
Q. What is the primary method of providing progress information to management during a project?
View solution
Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?
View solution
Q. How is project control maintained when the project is underway?
View solution
Q. What is the main concern when activities on the critical path slip?
View solution
Q. What is the main purpose of risk management?
View solution
Q. What are the three ways to handle risks?
View solution
Q. How does PERT offer simple yet powerful means to schedule and control activities within a project?
View solution
Suggested Topics
Are you eager to expand your knowledge beyond Software Engineering? We've curated a selection of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!