21. | The spiral model has two dimensions namely _____________ and ____________. |
a. | diagonal, angular |
b. | radial, perpendicular |
c. | radial, angular |
d. | diagonal, perpendicular |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (c).radial, angular
|
22. | How is WINWIN Spiral Model different from Spiral Model? |
a. | It defines tasks required to define resources, timelines, and other project related information. |
b. | It defines a set of negotiation activities at the beginning of each pass around the spiral. |
c. | It defines tasks required to assess both technical and management risks. |
d. | It defines tasks required to construct, test, install, and provide user support. |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (b).It defines a set of negotiation activities at the beginning of each pass around the spiral.
|
23. | Identify the disadvantage of Spiral Model. |
a. | Doesn’t work well for smaller projects |
b. | High amount of risk analysis |
c. | Strong approval and documentation control |
d. | Additional Functionality can be added at a later date |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (a).Doesn’t work well for smaller projects
|
24. | How is Incremental Model different from Spiral Model? |
a. | Progress can be measured for Incremental Model. |
b. | Changing requirements can be accommodated in Incremental Model. |
c. | Users can see the system early in Incremental Model. |
d. | no difference between these two |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (a).Progress can be measured for Incremental Model.
|
25. | If you were to create client/server applications, which model would you go for? |
a. | WINWIN Spiral Model |
b. | Spiral Model |
c. | Concurrent Model |
d. | Incremental Model |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (c).Concurrent Model
|
26. | Selection of a model is based on |
a. | Requirements |
b. | Development team |
c. | Users |
d. | All of the mentioned |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (d).All of the mentioned
|
27. | Which two models doesn’t allow defining requirements early in the cycle? |
a. | Waterfall & RAD |
b. | Prototyping & Spiral |
c. | Prototyping & RAD |
d. | Waterfall & Spiral |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (b).Prototyping & Spiral
|
28. | Which of the following life cycle model can be chosen if the development team has less experience on similar projects? |
a. | Spiral |
b. | Waterfall |
c. | RAD |
d. | Iterative Enhancement Model |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (a).Spiral
|
29. | If you were a lead developer of a software company and you are asked to submit a project/product within a stipulated time-frame with no cost barriers, which model would you select? |
a. | Waterfall |
b. | Spiral |
c. | RAD |
d. | Incremental |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (c).RAD
|
30. | Which two of the following models will not be able to give the desired outcome if user’s participation is not involved? |
a. | Waterfall & Spiral |
b. | RAD & Spiral |
c. | RAD & Waterfall |
d. | RAD & Prototyping |
View Answer Report Discuss Too Difficult! Search Google |
Answer: (d).RAD & Prototyping
|