What is the first step in risk management strategy?

a.

Identifying the risk factors

b.

Determining the risk exposure

c.

Developing strategies to mitigate the risks

d.

Handling risks

Posted under Software Engineering

Answer: (a).Identifying the risk factors Explanation:The first step in risk management strategy is to identify the risk factors that may impact the project. This involves creating a checklist of potential risks and assessing the likelihood and impact of each one. Once the risks have been identified, the organization can move on to determining the risk exposure, developing strategies to mitigate the risks, and continuously monitoring and handling the risks throughout the project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the first step in risk management strategy?

Similar Questions

Discover Related MCQs

Q. What is the risk exposure for a given risk factor?

Q. How is risk management a cyclic process?

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?