Question
a.
By using the earliest possible time at which activity can start
b.
By using the latest finishing time of all the predecessor nodes
c.
By using the set of successor nodes of N
d.
None of the above
Posted under Software Engineering
Engage with the Community - Add Your Comment
Confused About the Answer? Ask for Details Here.
Know the Explanation? Add it Here.
Q. How is the latest point in time at which activity L should finish computed?
Similar Questions
Discover Related MCQs
Q. What does a Gantt chart depict?
View solution
Q. What do the gray areas in the Gantt chart represent?
View solution
Q. What is the meaning of Si and Fi in the PERT technique?
View solution
Q. How is the earliest possible starting time of an activity computed?
View solution
Q. What is the earliest possible finishing time of the whole project?
View solution
Q. What is a critical path in PERT technique?
View solution
Q. What is the purpose of dummy activities in PERT technique?
View solution
Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?
View solution
Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?
View solution
Q. What is the purpose of a Gantt chart in the PERT technique?
View solution
Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?
View solution
Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?
View solution
Q. What is the purpose of a Gantt chart in project management?
View solution
Q. How can project expenditures be planned using a Gantt chart?
View solution
Q. What is used to determine cumulative effort and expenditure during a project?
View solution
Q. What is the primary method of providing progress information to management during a project?
View solution
Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?
View solution
Q. How is project control maintained when the project is underway?
View solution
Q. What is the main concern when activities on the critical path slip?
View solution
Q. What is the main purpose of risk management?
View solution
Suggested Topics
Are you eager to expand your knowledge beyond Software Engineering? We've curated a selection of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!