What is the risk exposure for a given risk factor?

a.

The probability that the risk will occur

b.

The effect of the risk on the project

c.

The probability multiplied by the effect (p*E)

d.

The cost of avoiding the risk

Answer: (c).The probability multiplied by the effect (p*E) Explanation:The risk exposure is a measure of the potential impact of a risk factor on the project. It is calculated by multiplying the probability of the risk occurring (p) by the potential impact or effect of the risk (E) on the project. This gives an overall measure of the potential risk to the project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the risk exposure for a given risk factor?

Similar Questions

Discover Related MCQs

Q. How is risk management a cyclic process?

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?