adplus-dvertising
frame-decoration

Question

What is the earliest possible starting time for an unlabeled node?

a.

The earliest possible time at which activity can start

b.

The latest finishing time of all the predecessor nodes

c.

The corresponding finishing time

d.

None of the above

Posted under Software Engineering

Answer: (b).The latest finishing time of all the predecessor nodes Explanation:For all unlabeled nodes whose predecessors are all labeled nodes, the earliest possible starting time is the latest finishing time of all the predecessor nodes.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the earliest possible starting time for an unlabeled node?

Similar Questions

Discover Related MCQs

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. What is the primary method of providing progress information to management during a project?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. How is project control maintained when the project is underway?