adplus-dvertising
frame-decoration

Question

What is the purpose of PERT charts?

a.

To depict the set of activities and their constraints in a network

b.

To compute the earliest possible point in time at which the project can be completed

c.

To reflect the decomposition of a project into subtasks

d.

To measure and control progress

Posted under Software Engineering

Answer: (a).To depict the set of activities and their constraints in a network Explanation:PERT charts, or Program Evaluation and Review Technique, are network diagrams that depict the set of activities and their constraints in a network. They are also used to compute the earliest possible point in time at which the project can be completed by identifying the start and end nodes and determining the duration of each activity.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the purpose of PERT charts?

Similar Questions

Discover Related MCQs

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. What is the primary method of providing progress information to management during a project?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?