Question

Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

a.

Risks related to customers and users (C1)

b.

Risks related to the scope and requirements of the project (C2)

c.

Risks related to the execution of the project (C3)

d.

Both b and c

Posted under Software Engineering

Answer: (d).Both b and c Explanation:From a study of a large number of projects, Wallace and Keil (2004) found that risk categories C2 and C3 affect project outcomes most. They also found that execution risks (C3) are much more important in explaining process outcome that scope or requirements risks.