adplus-dvertising
frame-decoration

Question

Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

a.

Risks related to customers and users (C1)

b.

Risks related to the scope and requirements of the project (C2)

c.

Risks related to the execution of the project (C3)

d.

Both b and c

Answer: (d).Both b and c Explanation:From a study of a large number of projects, Wallace and Keil (2004) found that risk categories C2 and C3 affect project outcomes most. They also found that execution risks (C3) are much more important in explaining process outcome that scope or requirements risks.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?