Question

How is risk management a cyclic process?

a.

Risk factors must be monitored and re-evaluated regularly

b.

Risks are handled by re-assessing the project, invoking a contingency plan, or transferring to crisis mode

c.

Both A and B

d.

None of the above

Posted under Software Engineering

Answer: (c).Both A and B Explanation:Risk management is a cyclic process because it involves a series of steps that are repeated over the course of a project. These steps include identifying and assessing risks, developing strategies to mitigate or avoid risks, monitoring and controlling risks, and evaluating the effectiveness of risk management activities. This cyclic process allows for the ongoing identification, analysis and management of risks throughout the project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is risk management a cyclic process?

Similar Questions

Discover Related MCQs

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?