adplus-dvertising
frame-decoration

Question

What is the meaning of Si and Fi in the PERT technique?

a.

The earliest possible time at which activity can start and finish

b.

The latest possible time at which activity can start and finish

c.

The current time of activity

d.

The time it took to complete an activity

Posted under Software Engineering

Answer: (a).The earliest possible time at which activity can start and finish Explanation:Si and Fi in PERT technique denotes the earliest possible time at which activity can start and finish, respectively.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the meaning of Si and Fi in the PERT technique?

Similar Questions

Discover Related MCQs

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. What is the primary method of providing progress information to management during a project?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. How is project control maintained when the project is underway?

Q. What is the main concern when activities on the critical path slip?

Q. What is the main purpose of risk management?

Q. What are the three ways to handle risks?

Q. How does PERT offer simple yet powerful means to schedule and control activities within a project?