What are constraints in project planning?

a.

A relation between tasks that can be expressed as temporal relations

b.

A way to limit resource usage

c.

A way to satisfy project requirements

d.

A way to measure progress

Posted under Software Engineering

Answer: (a).A relation between tasks that can be expressed as temporal relations Explanation:Constraints in project planning are relations between tasks that can be expressed as temporal relations, such as activities that must be executed in a specific order.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What are constraints in project planning?

Similar Questions

Discover Related MCQs

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?

Q. What does a Gantt chart depict?

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?