adplus-dvertising
frame-decoration

Question

What do the gray areas in the Gantt chart represent?

a.

The total duration of the project

b.

The slack or float times of activities

c.

The earliest possible finishing time of the whole project

d.

None of the above

Posted under Software Engineering

Answer: (b).The slack or float times of activities Explanation:The gray areas in the Gantt chart represent slack or float times of activities, which indicate that the corresponding activity may consume more than its estimated time, or start later than the earliest possible starting time, without affecting the total duration of the project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What do the gray areas in the Gantt chart represent?

Similar Questions

Discover Related MCQs

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. What is the primary method of providing progress information to management during a project?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. How is project control maintained when the project is underway?

Q. What is the main concern when activities on the critical path slip?

Q. What is the main purpose of risk management?

Q. What are the three ways to handle risks?

Q. How does PERT offer simple yet powerful means to schedule and control activities within a project?