adplus-dvertising
frame-decoration

Question

What does a Gantt chart depict?

a.

The duration of the project

b.

The time span of each activity

c.

The earliest possible finishing time of the whole project

d.

None of the above

Answer: (b).The time span of each activity Explanation:In a Gantt chart, the time span of each activity is depicted by the length of a segment drawn on an adjacent calendar.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What does a Gantt chart depict?

Similar Questions

Discover Related MCQs

Q. What do the gray areas in the Gantt chart represent?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the earliest possible finishing time of the whole project?

Q. What is a critical path in PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the purpose of a Gantt chart in project management?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. What is the primary method of providing progress information to management during a project?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. How is project control maintained when the project is underway?

Q. What is the main concern when activities on the critical path slip?

Q. What is the main purpose of risk management?

Q. What are the three ways to handle risks?