Question

What is the main advantage of using Object Points in the Application Composition model?

a.

Object Points are easier to determine than Function Points

b.

Object Points reflect the batch-oriented world of the 1970s

c.

Object Points are more accurate than Function Points

d.

Object Points are user-oriented measure of system function

Answer: (a).Object Points are easier to determine than Function Points Explanation:The Application Composition model is based on counting Object Points which are considered to be easier to determine and at an earlier point in time than Function Points.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main advantage of using Object Points in the Application Composition model?

Similar Questions

Discover Related MCQs

Q. How is the total effort in the Application Composition model estimated?

Q. How does the Post-Architecture model differ from the original COCOMO model?

Q. What are the differences between the COCOMO and COCOMO 2 set of cost drivers?

Q. What is the formula used to determine the exponent b in the COCOMO 2 effort equation?

Q. Can both KSLOC and UFP be used as a base measure in COCOMO 2?

Q. How is the effort estimated in the Application Composition model of COCOMO 2?

Q. How does COCOMO 2 handle reuse?

Q. What are the five scale factors used in COCOMO 2?

Q. How is reuse catered for in the original COCOMO model?

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?