adplus-dvertising
frame-decoration

Question

What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

a.

0% to 50%

b.

10% to 20%

c.

0% to 8%

d.

20% to 30%

Answer: (c).0% to 8% Explanation:The degree of assessment and assimilation (AA) in COCOMO 2 denotes the effort needed to determine whether a component is appropriate for the present application. It ranges from 0% (no extra effort required) to 8% (extensive test, evaluation and documentation required).

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Similar Questions

Discover Related MCQs

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?

Q. What is the benefit of combining different estimation methods?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?

Q. What is the potential effect of experience on cost estimates in software development projects?