Question

What is the formula used to determine the exponent b in the COCOMO 2 effort equation?

a.

b = 1.01 + 0.01 * ΣXi

b.

b = 1.01 + 0.01 * ΣWi

c.

b = 1.01 + 0.01 * ΣXi * ΣWi

d.

b = 1.01 + 0.01 * ΣYi

Posted under Software Engineering

Answer: (b).b = 1.01 + 0.01 * ΣWi Explanation:The exponent b for the effort equation in COCOMO 2 is determined by the formula: b = 1.01 + 0.01 * ΣWi where Wi are the five scale factors rated on a six-point scale from very low (5) to extra high (0).

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the formula used to determine the exponent b in the COCOMO 2 effort equation?

Similar Questions

Discover Related MCQs

Q. Can both KSLOC and UFP be used as a base measure in COCOMO 2?

Q. How is the effort estimated in the Application Composition model of COCOMO 2?

Q. How does COCOMO 2 handle reuse?

Q. What are the five scale factors used in COCOMO 2?

Q. How is reuse catered for in the original COCOMO model?

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?