How is the equivalent number of new lines of code calculated in COCOMO 2?

a.

by multiplying the number of lines of code by the adjustment factor AAF

b.

by multiplying the number of lines of code by ( AAF+SU+AA )/100

c.

by subtracting the number of reused lines of code from the total number of lines of code

d.

not calculated

Posted under Software Engineering

Answer: (b).by multiplying the number of lines of code by ( AAF+SU+AA )/100 Explanation:In COCOMO 2, the equivalent number of new lines of code is calculated by multiplying the number of lines of code by (AAF+SU+AA)/100, where AAF is the adjustment factor, SU is the software understanding increment, and AA is the degree of assessment and assimilation.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Similar Questions

Discover Related MCQs

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?