What are the five scale factors used in COCOMO 2?

a.

Prencedentedness, development flexibility, architecture/risk resolution, team cohesion, process maturity

b.

Novelty, conformance, risk elimination, stakeholder interactions, project organization maturity

c.

Novelty, flexibility, risk resolution, team dynamics, maturity of project organization

d.

Prencedentedness, flexibility, risk management, team dynamics, project maturity

Answer: (a).Prencedentedness, development flexibility, architecture/risk resolution, team cohesion, process maturity Explanation:The five scale factors used in COCOMO 2 are Prencedentedness, development flexibility, architecture/risk resolution, team cohesion, and process maturity. These factors account for the novelty of the project, the need for conformance with pre-established and external interface requirements, the percentage of significant risks that have been eliminated, possible difficulties in stakeholder interactions, and the maturity of the project organization according to the Capability Maturity Model.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What are the five scale factors used in COCOMO 2?

Similar Questions

Discover Related MCQs

Q. How is reuse catered for in the original COCOMO model?

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?