Question

How is reuse catered for in the original COCOMO model?

a.

by adjusting the unadjusted value KLOC using a formula

b.

by considering the fractions of the system that require redesign, recoding, and re-integration

c.

by using a different set of cost drivers

d.

by using a different exponent in the effort equation

Posted under Software Engineering

Answer: (b).by considering the fractions of the system that require redesign, recoding, and re-integration Explanation:In the original COCOMO model, reuse is catered for by separately considering the fractions of the system that require redesign, recoding, and re-integration. An adjustment factor AAF is then given by the formula AAF = 0.4DM + 0.3CM + 0.3IM. An adjusted value AKLOC, given by AKLOC = KLOC * AAF/100 is next used in the COCOMO formulae, instead of the unadjusted value KLOC. This way, a lower cost estimate is obtained if part of the system is reused.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is reuse catered for in the original COCOMO model?

Similar Questions

Discover Related MCQs

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?