Question

According to DeMarco, what is the main cause of politically-colored estimates?

a.

Lack of data about past projects

b.

Lack of expertise in the estimators

c.

Political arguments entering the arena

d.

Difficulty in collecting data

Posted under Software Engineering

Answer: (c).Political arguments entering the arena Explanation:According to DeMarco, politically-colored estimates can have disastrous effects and political arguments almost always play a role if estimates are being given by people directly involved in the project, such as the project manager, or someone reporting to the project manager.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Similar Questions

Discover Related MCQs

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?

Q. What is the benefit of combining different estimation methods?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?

Q. What is the potential effect of experience on cost estimates in software development projects?

Q. What is the result of combining sufficiently different estimation methods?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?