Question

How does COCOMO 2 handle reuse?

a.

By separately considering the fractions of the system that require redesign, recoding, and re-integration

b.

By accounting for the novelty of the project to the development organization

c.

By considering the percentage of significant risks that have been eliminated

d.

By reflecting the maturity of the project organization according to the Capability Maturity Model

Posted under Software Engineering

Answer: (a).By separately considering the fractions of the system that require redesign, recoding, and re-integration Explanation:In COCOMO 2, reuse is handled by separately considering the fractions of the system that require redesign, recoding, and re-integration, and using an adjustment factor (AAF) to lower the cost estimate if part of the system is reused.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How does COCOMO 2 handle reuse?

Similar Questions

Discover Related MCQs

Q. What are the five scale factors used in COCOMO 2?

Q. How is reuse catered for in the original COCOMO model?

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?