Question

How is the effort estimated in the Application Composition model of COCOMO 2?

a.

by counting the number of screens, reports, and 3GL components in the application

b.

by determining the complexity level of each screen and report

c.

by using numbers given in a classification table similar to those in FPA

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:In the Application Composition model of COCOMO 2, the total effort is estimated by counting the number of screens, reports, and 3GL components in the application, determining the complexity level of each screen and report, using numbers given in a classification table similar to those in FPA, and summing the Object Points for the individual objects.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is the effort estimated in the Application Composition model of COCOMO 2?

Similar Questions

Discover Related MCQs

Q. How does COCOMO 2 handle reuse?

Q. What are the five scale factors used in COCOMO 2?

Q. How is reuse catered for in the original COCOMO model?

Q. How is the exponent b in the COCOMO 2 effort equation determined?

Q. How is the effort needed to determine whether a component is appropriate for the present application represented in COCOMO 2?

Q. How is the equivalent number of new lines of code calculated in COCOMO 2?

Q. What are the factors that impact the cost of reuse in COCOMO 2?

Q. What is the extra effort needed to reuse code if it is strongly modular, matches the application, and is well-documented?

Q. What is the range of the degree of assessment and assimilation (AA) in COCOMO 2?

Q. How is the equivalent kilo number of new lines of code (EKLOC) calculated in COCOMO 2?

Q. What is one of the main problems in applying cost estimation models?

Q. According to DeMarco, what is the main cause of politically-colored estimates?

Q. What is the "budget" method of cost estimation?

Q. What is the "price to win" method of cost estimation?

Q. What is one of the main reasons for the lack of data collection in software projects?

Q. What is one of the main traps to be avoided when using other methods for cost estimation based on the expertise of estimators?

Q. What is the main disadvantage of politically-colored estimates?

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?