Question

How can project expenditures be planned using a Gantt chart?

a.

By listing all activities and indicating their earliest starting time and latest ending time on the calendar

b.

By recording time spent per activity per project member on time cards

c.

By using the information contained in the Gantt chart and knowledge of personnel resources required for each activity to establish a personnel plan

d.

By monitoring the project's progress and expenditures

Answer: (c).By using the information contained in the Gantt chart and knowledge of personnel resources required for each activity to establish a personnel plan Explanation:Using the information contained in the Gantt chart and knowledge of personnel resources required for each activity, a personnel plan can be established indicating how many people are required in each unit of time, which provides a direct means to plan project expenditures.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How can project expenditures be planned using a Gantt chart?

Similar Questions

Discover Related MCQs

Q. What is the purpose of a Gantt chart in project management?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What is a critical path in PERT technique?

Q. What is the earliest possible finishing time of the whole project?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. What do the gray areas in the Gantt chart represent?

Q. What does a Gantt chart depict?

Q. How is the latest point in time at which activity L should finish computed?

Q. What is the corresponding finishing time for an unlabeled node?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the purpose of PERT charts?

Q. What is a PERT chart?

Q. What are constraints in project planning?

Q. What is a milestone in project planning and control?