adplus-dvertising
frame-decoration

Question

What is the Winner's curse phenomenon known from auctions?

a.

The highest bid wins, but the winner may be left with an item that's worth less than paid for

b.

The lowest bid wins, but the winner may be left with an item that's worth more than paid for

c.

The highest bid wins, and the winner is guaranteed that the item is worth what they paid for

d.

None of the above

Answer: (a).The highest bid wins, but the winner may be left with an item that's worth less than paid for Explanation:The Winner's curse phenomenon is known from auctions, where players are uncertain of the value of a good when they bid and the highest bid wins, but the winner may be left with an item that's worth less than paid for.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the Winner's curse phenomenon known from auctions?

Similar Questions

Discover Related MCQs

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?

Q. What is the benefit of combining different estimation methods?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?

Q. What is the potential effect of experience on cost estimates in software development projects?

Q. What is the result of combining sufficiently different estimation methods?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?

Q. What is the main issue with using the comparison method for cost estimation?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the impact of software on a project's estimated effort?

Q. What is the impact of training on software cost estimation?

Q. How do requirements set or proposed affect the cost estimate?

Q. Is it advisable to make a cost estimate if it is not needed?