Question

What is the main disadvantage of politically-colored estimates?

a.

They are not accurate

b.

They are not reliable

c.

They can have disastrous effects

d.

They are not based on past data

Posted under Software Engineering

Answer: (c).They can have disastrous effects Explanation:The politically-colored estimates can have disastrous effects as they have been shown all too often during the short history of the field.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main disadvantage of politically-colored estimates?

Similar Questions

Discover Related MCQs

Q. According to Jørgensen (2005) what should be avoided in expert-based effort estimation?

Q. What is the goal of estimation according to Jørgensen (2005)?

Q. What is the Winner's curse phenomenon known from auctions?

Q. What type of contracts do software clients generally require according to Jørgensen and Grimstad (2004)?

Q. What is the phenomenon known as "winner's curse" in software field?

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?

Q. What is the benefit of combining different estimation methods?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?

Q. What is the potential effect of experience on cost estimates in software development projects?

Q. What is the result of combining sufficiently different estimation methods?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?

Q. What is the main issue with using the comparison method for cost estimation?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the impact of software on a project's estimated effort?