adplus-dvertising
frame-decoration

Question

How is project control maintained when the project is underway?

a.

By monitoring project expenditures

b.

By renegotiating the project's schedule

c.

By producing milestone reports

d.

By monitoring the project's progress and expenditures

Posted under Software Engineering

Answer: (d).By monitoring the project's progress and expenditures Explanation:Project control is based on monitoring the project's progress and expenditures, and that time spent per activity per project member is recorded on time cards.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is project control maintained when the project is underway?

Similar Questions

Discover Related MCQs

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. What is the primary method of providing progress information to management during a project?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is the purpose of a Gantt chart in project management?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What is a critical path in PERT technique?

Q. What is the earliest possible finishing time of the whole project?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. What do the gray areas in the Gantt chart represent?

Q. What does a Gantt chart depict?

Q. How is the latest point in time at which activity L should finish computed?

Q. What is the corresponding finishing time for an unlabeled node?

Q. What is the earliest possible starting time for an unlabeled node?