What is the risk exposure of a risk?

a.

The probability that the risk will occur

b.

The effect that the risk will have on the project

c.

The combination of the probability and the effect of the risk

d.

The amount of money allocated for handling the risk

Answer: (c).The combination of the probability and the effect of the risk Explanation:The risk exposure of a risk is the combination of the probability that the risk will occur and the effect that it will have on the project. It is calculated by multiplying the probability by the effect, or p*E.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the risk exposure of a risk?

Similar Questions

Discover Related MCQs

Q. How often should the risk management process be carried out?

Q. What are the four types of risks identified by Wallace and Keil (2004)?

Q. What is the first step in risk management strategy?

Q. What is the risk exposure for a given risk factor?

Q. How is risk management a cyclic process?

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?

Q. What is the corresponding finishing time for an unlabeled node?

Q. How is the latest point in time at which activity L should finish computed?