Question

What is the final step in risk management?

a.

Identifying the risk factors

b.

Developing strategies to mitigate the risks

c.

Handle risks

d.

Providing for a contingency plan

Answer: (c).Handle risks Explanation:The final step in risk management is handle risks. Risk factors must be monitored. For some risks, the avoidance or transfer actions may succeed, and those risks will never become a problem. However, for those risks that are decided not to handle, or for risks that become a problem despite mitigation efforts, a contingency plan must be invoked or the risk must be reassessed and handled. Risk management is a cyclic process.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the final step in risk management?

Similar Questions

Discover Related MCQs

Q. What is the main goal of risk management?

Q. What is the risk exposure of a risk?

Q. How often should the risk management process be carried out?

Q. What are the four types of risks identified by Wallace and Keil (2004)?

Q. What is the first step in risk management strategy?

Q. What is the risk exposure for a given risk factor?

Q. How is risk management a cyclic process?

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?

Q. What is a PERT chart?

Q. What is the purpose of PERT charts?

Q. What is the earliest possible starting time for an unlabeled node?