Dive deep into the fascinating world of Software Metrics with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Software Metrics, a crucial aspect of Software Engineering. In this section, you will encounter a diverse range of MCQs that cover various aspects of Software Metrics, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Software Engineering.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Software Metrics. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Software Engineering.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Software Metrics. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Software Metrics MCQs | Page 7 of 9

Explore more Topics under Software Engineering

Q61.
Process model is represented by
Discuss
Answer: (a).CMMI
Q62.
Process area in which organizational innovation and deployment casual analysis and resolution is present, focus on
Discuss
Answer: (a).continuous process improvement
Q63.
Capability level in which all level 3 criteria have been achieved and process area is controlled and improved using measurement and quality assessment in
Discuss
Answer: (d).Level4:Quantitatively Managed
Q64.
Process area which defines and focus on organizational process and training is focus on
Discuss
Answer: (b).process standardization
Q65.
CCMI model which describes a process in two dimensions is
Discuss
Answer: (a).continuous model
Q66.
Process area which defines and focus on organizational process and training is present in level of
Discuss
Answer: (b).defined
Q67.
Project planning is defined by CMMI for category
Discuss
Answer: (a).project management
Q68.
CMMI process model can be represented by
Discuss
Answer: (b).two ways
Discuss
Answer: (c).Capability Maturity Model Integration
Q70.
In plan-do-check-act cycle, establishment of process objectives, activities and task necessary to achieve high quality software is accomplished by
Discuss
Answer: (a).plan
Page 7 of 9