Dive deep into the fascinating world of Software Management with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Software Management, a crucial aspect of Software Engineering. In this section, you will encounter a diverse range of MCQs that cover various aspects of Software Management, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Software Engineering.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Software Management. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Software Engineering.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Software Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Software Management MCQs | Page 23 of 25

Explore more Topics under Software Engineering

Q221.
What is an example of a product line in software development?
Discuss
Answer: (a).ACK (Amsterdam Compiler Kit) Explanation:ACK (Amsterdam Compiler Kit) is an example of a product line in software development, where different configurations of the system can be assembled to create compilers for different languages and machines.
Discuss
Answer: (a).It is the management of all artifacts produced in the course of a software development project. Explanation:Configuration management is the management of all artifacts produced in the course of a software development project.
Discuss
Answer: (b).It is a shared project database containing all approved items and supported by tools to assist in retrieving and updating its elements. Explanation:A baseline is β€˜a specification or product that has been formally reviewed and agreed upon, that serves as the basis for further development, and that can be changed only through formal change control procedures’ (IEEE610, 1990). It is the shared project database containing all approved items and supported by tools to assist in retrieving and updating its elements.
Discuss
Answer: (b).They are a set of artifacts produced during the development of a software system and treated as a single entity in the configuration management process Explanation:Configuration items are β€˜an aggregation of hardware, software, or both, that is designated for configuration management and treated as a single entity in the configuration management process’ (IEEE610, 1990). Possible configuration items are: source code components, the requirements specification, the design documentation, the test plan, test cases, test results, the user manual.
Discuss
Answer: (a).To maintain the integrity of the set of artifacts. Explanation:A major task of configuration management is to maintain the integrity of this set of artifacts. It is important to keep the consistency and correctness of the set of artifacts.
Discuss
Answer: (a).It is concerned with the management of all artifacts produced in the course of a software development project. Explanation:Configuration management is concerned with the management of all artifacts produced in the course of a software development project.
Discuss
Answer: (b).Requirements specification, design documents, test plan, test cases, test results and user manual Explanation:Possible configuration items are requirements specification, design documents, source code components, test plan, test cases, test results and user manual
Discuss
Answer: (d).All of the above Explanation:The CCB ensures that any change to the baseline is properly authorized and executed, and it assesses change request and make sure that all configuration items affected will eventually be updated accordingly.
Discuss
Answer: (d).All of the above Explanation:Configuration management is concerned with the management of all artifacts produced in the course of a software development project, which includes keeping track of different versions of elements of a system, managing workflow management tasks, etc.
Q230.
What is the name of the shared project database that contains all approved items?
Discuss
Answer: (a).Baseline Explanation:Baseline is the shared project database that contains all approved items and serves as the basis for further development.