What is a common way to deal with communication problems when a project involves more than one development site?

a.

By paying attention to socialization issues

b.

By choosing an evolutionary development strategy

c.

By having users participate in design reviews

d.

By listing the requirements

Posted under Software Engineering

Answer: (a).By paying attention to socialization issues Explanation:When a project involves more than one development site, communication problems may arise. A common way to deal with this risk is by paying attention to socialization issues, such as scheduling site visits, in order to improve communication and collaboration among team members at different sites.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is a common way to deal with communication problems when a project involves more than one development site?

Similar Questions

Discover Related MCQs

Q. What are the three general strategies to mitigate risks?

Q. What is the process of determining the risk exposure?

Q. What is the final step in risk management?

Q. What is the main goal of risk management?

Q. What is the risk exposure of a risk?

Q. How often should the risk management process be carried out?

Q. What are the four types of risks identified by Wallace and Keil (2004)?

Q. What is the first step in risk management strategy?

Q. What is the risk exposure for a given risk factor?

Q. How is risk management a cyclic process?

Q. Which of the following categories of risks have the most impact on project outcomes, according to a study by Wallace and Keil (2004)?

Q. What is the suggested ordering of risks that managers should pay attention to, according to Wallace and Keil's study?

Q. What is the advice given by Tom Gilb in regards to managing risks?

Q. Which of the following risks can be mitigated through an agile approach?

Q. What is a work breakdown structure (WBS)?

Q. What is a milestone in a project?

Q. What is the purpose of project planning?

Q. What is the purpose of a work breakdown structure (WBS)?

Q. What is a milestone in project planning and control?

Q. What are constraints in project planning?