adplus-dvertising

Welcome to the Software Management MCQs Page

Dive deep into the fascinating world of Software Management with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Software Management, a crucial aspect of Software Engineering. In this section, you will encounter a diverse range of MCQs that cover various aspects of Software Management, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Software Engineering.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Software Management. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Software Engineering.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Software Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Software Management MCQs | Page 9 of 25

Q81.
How many forms exists of Barry Boehm’s COCOMO Model?
Discuss
Answer: (b).Three
Q82.
Who suggested the four different approaches to the sizing problem?
Discuss
Answer: (d).Putnam and Myers
Q83.
In many cases, it is often more cost effective to acquire, rather than develop, computer software.
Discuss
Answer: (a).True
Discuss
Answer: (d).All of the mentioned
Q85.
Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition?
Discuss
Answer: (c).External process
Q86.
The project planner must reconcile the estimates based on decomposition techniques to produce a single estimate of effort.
Discuss
Answer: (b).False
Q87.
Programming language experience is a part of which factor of COCOMO cost drivers?
Discuss
Answer: (a).Personnel Factor
Q88.
If an Indirect approach is taken, then the sizing approach is represented as
Discuss
Answer: (b).FP
Q89.
Project management involves the planning, monitoring, and control of the people, process, and events that occur as software evolves from a preliminary concept to an operational implementation.
Discuss
Answer: (a).True
Q90.
Which of the following is not an effective software project management focus?
Discuss
Answer: (c).popularity

Suggested Topics

Are you eager to expand your knowledge beyond Software Engineering? We've curated a selection of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!