Question

According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

a.

Mix estimation, planning and bidding

b.

Combine estimation methods

c.

Ask for justification

d.

Select experts with experience from similar projects

Posted under Software Engineering

Answer: (b).Combine estimation methods Explanation:Jorgensen (2005) states that the politically-colored estimation methods mix up estimation, planning and bidding, and provides the guidelines of combining estimation methods, asking for justification, selecting experts with experience from similar projects, accept and assess uncertainty, provide learning opportunities, and consider postponing or avoiding effort estimation to avoid these methods.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. According to Jorgensen (2005), what should be done to avoid the politically-colored estimation methods?

Similar Questions

Discover Related MCQs

Q. What is the outcome of a contract that results in low or negative profits to the bidder?

Q. What is the main goal of estimation?

Q. According to Jorgensen and Grimstad (2004), what is the result of companies with the lowest bids in an experiment they conducted?

Q. What is the benefit of combining different estimation methods?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?

Q. What is the potential effect of experience on cost estimates in software development projects?

Q. What is the result of combining sufficiently different estimation methods?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?

Q. What is the main issue with using the comparison method for cost estimation?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the impact of software on a project's estimated effort?

Q. What is the impact of training on software cost estimation?

Q. How do requirements set or proposed affect the cost estimate?

Q. Is it advisable to make a cost estimate if it is not needed?

Q. How does shortening the development time of a project affect the manpower required?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?