Question

What is the main purpose of COCOMO 2?

a.

To provide a revision of the 1981 COCOMO model

b.

To learn about significant changes in the software development industry

c.

To offer a means to estimate costs for different types of projects

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:COCOMO 2 is a revision of the 1981 COCOMO model that has been tuned to the life cycle practices of the 1990s and 2000s. It reflects the experience and knowledge of cost estimation, and provides three increasingly detailed cost estimation models for different types of projects, as well as during different stages of a single project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main purpose of COCOMO 2?

Similar Questions

Discover Related MCQs

Q. What are the three models provided by COCOMO 2?

Q. What is the basis of the Application Composition model in COCOMO 2?

Q. What is the main difference between Function Points used in FPA and Object Points used in the Application Composition model of COCOMO 2?

Q. What is the main advantage of Object Points over Function Points?

Q. What is the main use of the Application Composition model in COCOMO 2?

Q. How is the complexity level of each screen and report determined in the Application Composition model?

Q. How is the total effort estimated in the Application Composition model?

Q. How is the reuse percentage determined in the Application Composition model?

Q. What is the productivity rate used in the Application Composition model?

Q. What is the main purpose of the Application Composition model in COCOMO 2?

Q. How are Object Points determined in the Application Composition model?

Q. How is the number of function points determined in the Early Design model?

Q. What is the main difference between the Application Composition model and the Early Design model in COCOMO 2?

Q. What is the main advantage of using Object Points in the Application Composition model?

Q. How is the total effort in the Application Composition model estimated?

Q. How does the Post-Architecture model differ from the original COCOMO model?

Q. What are the differences between the COCOMO and COCOMO 2 set of cost drivers?

Q. What is the formula used to determine the exponent b in the COCOMO 2 effort equation?

Q. Can both KSLOC and UFP be used as a base measure in COCOMO 2?

Q. How is the effort estimated in the Application Composition model of COCOMO 2?