Question

How does PERT offer simple yet powerful means to schedule and control activities within a project?

a.

By depicting the set of activities and their temporal relations in a graph

b.

By identifying the critical path

c.

By determining the probability that a risk will happen

d.

By hiring more people to mitigate risks

Posted under Software Engineering

Answer: (a).By depicting the set of activities and their temporal relations in a graph Explanation:PERT offers simple yet powerful means to schedule and control activities within a project by depicting the set of activities and their temporal relations in a graph. This allows project managers to easily see the dependencies between activities and make adjustments as necessary.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How does PERT offer simple yet powerful means to schedule and control activities within a project?

Similar Questions

Discover Related MCQs

Q. What are the three ways to handle risks?

Q. What is the main purpose of risk management?

Q. What is the main concern when activities on the critical path slip?

Q. How is project control maintained when the project is underway?

Q. What is the primary action management needs to take when there is schedule slippage of activities on a critical path?

Q. What is the primary method of providing progress information to management during a project?

Q. What is used to determine cumulative effort and expenditure during a project?

Q. How can project expenditures be planned using a Gantt chart?

Q. What is the purpose of a Gantt chart in project management?

Q. What is the purpose of dummy activities in an activity-on-arrow network in the PERT technique?

Q. What is the difference between an "activity-on-node" network and an "activity-on-arrow" network in the PERT technique?

Q. What is the purpose of a Gantt chart in the PERT technique?

Q. What does the "Fi" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What does the "Si" in the ordered pair (Si, Fi) represent in the PERT technique?

Q. What is the purpose of dummy activities in PERT technique?

Q. What is a critical path in PERT technique?

Q. What is the earliest possible finishing time of the whole project?

Q. How is the earliest possible starting time of an activity computed?

Q. What is the meaning of Si and Fi in the PERT technique?

Q. What do the gray areas in the Gantt chart represent?