How many control situations can be derived from the three dimensions of product certainty, process certainty and resource certainty?

a.

Four

b.

Two

c.

Eight

d.

Six

Posted under Software Engineering

Answer: (c).Eight Explanation:If we allow each of the three certainty factors (product certainty, process certainty, and resource certainty) to take one of two values (high and low), we get eight control situations. However, some of these situations are not very realistic, so the actual number of control situations that can be derived may be less than eight.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How many control situations can be derived from the three dimensions of product certainty, process certainty and resource certainty?

Similar Questions

Discover Related MCQs

Q. What is the main emphasis in a situation where the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What type of process model may be used in a situation where the requirements are known and stable?

Q. What is the preferred method of coordination in a situation where the requirements are known and stable?

Q. How can cost estimation be done in a situation where the requirements are known and stable?

Q. What is the main emphasis when the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What is the main problem when there is uncertainty as regards resources?

Q. How can activities be coordinated in a project where there is uncertainty about resources?

Q. What development strategy can be used when there is uncertainty about resources?

Q. What is the primary problem in a situation where requirements are known and stable, but there is uncertainty regarding resources?

Q. What is the main problem in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?

Q. What is the recommended approach for controlling a project in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?

Q. What is the recommended approach for cost estimation in a situation where there is uncertainty regarding resources?

Q. How can one manage a project where the requirements are fixed and stable, but there is uncertainty in the process and resources?

Q. What is the main problem when there is uncertainty in the resources?

Q. What is the coordination mechanism for type of project where the product certainty, process certainty and resource certainty are all low?

Q. What is the main goal in making this type of project manageable where the product certainty, process certainty and resource certainty are all low?

Q. What is the appropriate process model for type of project where the product certainty, process certainty and resource certainty are all low?

Q. Is it feasible to use formalized cost estimation models for type of project where the product certainty, process certainty and resource certainty are all low?

Q. How can cost estimates be used for type of project where the product certainty, process certainty and resource certainty are all low?

Q. What is the recommended approach for coordinating work at the macro level in big projects?