adplus-dvertising
frame-decoration

Question

What is the main emphasis when the requirements are known and stable, and there is sufficient control variety and resources available?

a.

Coordination of activities

b.

Realization of the software

c.

Cost estimation

d.

Staffing the project

Answer: (b).Realization of the software Explanation:The main emphasis in this situation is on how to achieve the goal effectively given the known and stable requirements.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main emphasis when the requirements are known and stable, and there is sufficient control variety and resources available?

Similar Questions

Discover Related MCQs

Q. What is the main problem when there is uncertainty as regards resources?

Q. How can activities be coordinated in a project where there is uncertainty about resources?

Q. What development strategy can be used when there is uncertainty about resources?

Q. What is the primary problem in a situation where requirements are known and stable, but there is uncertainty regarding resources?

Q. What is the main problem in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?

Q. What is the recommended approach for controlling a project in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?

Q. What is the recommended approach for cost estimation in a situation where there is uncertainty regarding resources?

Q. How can one manage a project where the requirements are fixed and stable, but there is uncertainty in the process and resources?

Q. What is the main problem when there is uncertainty in the resources?

Q. What is the coordination mechanism for type of project where the product certainty, process certainty and resource certainty are all low?

Q. What is the main goal in making this type of project manageable where the product certainty, process certainty and resource certainty are all low?

Q. What is the appropriate process model for type of project where the product certainty, process certainty and resource certainty are all low?

Q. Is it feasible to use formalized cost estimation models for type of project where the product certainty, process certainty and resource certainty are all low?

Q. How can cost estimates be used for type of project where the product certainty, process certainty and resource certainty are all low?

Q. What is the recommended approach for coordinating work at the macro level in big projects?

Q. Is it recommended to use the same control mechanisms at the macro and micro level in big projects?

Q. What are the consequences of neglecting project-specific characteristics during the planning stage of a software development project?

Q. What is the goal of tailoring the project's management to the situation at hand?

Q. What is the control situation that involves the most uncertainty?

Q. What is the main focus of the risk management in software development?