adplus-dvertising
frame-decoration

Question

What is the main goal in making this type of project manageable where the product certainty, process certainty and resource certainty are all low?

a.

Adhering to a strict budget

b.

Assigning clear responsibilities

c.

Maximizing output

d.

Keeping extra personnel

Answer: (c).Maximizing output Explanation:To make a project of this kind manageable, our goal will be to maximize output, given the resources available to the project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main goal in making this type of project manageable where the product certainty, process certainty and resource certainty are all low?

Similar Questions

Discover Related MCQs

Q. What is the appropriate process model for type of project where the product certainty, process certainty and resource certainty are all low?

Q. Is it feasible to use formalized cost estimation models for type of project where the product certainty, process certainty and resource certainty are all low?

Q. How can cost estimates be used for type of project where the product certainty, process certainty and resource certainty are all low?

Q. What is the recommended approach for coordinating work at the macro level in big projects?

Q. Is it recommended to use the same control mechanisms at the macro and micro level in big projects?

Q. What are the consequences of neglecting project-specific characteristics during the planning stage of a software development project?

Q. What is the goal of tailoring the project's management to the situation at hand?

Q. What is the control situation that involves the most uncertainty?

Q. What is the main focus of the risk management in software development?

Q. What is a common attitude towards risks in software development?

Q. What is the recommended approach for dealing with risks in a software project?

Q. What is the difference between a risk and a problem?

Q. What is the importance of identifying risks early on in a software development project?

Q. How can unstable, immature, unrealistic, or excessive requirements be dealt with as a risk in a software development project?

Q. What is a common way to deal with communication problems when a project involves more than one development site?

Q. What are the three general strategies to mitigate risks?

Q. What is the process of determining the risk exposure?

Q. What is the final step in risk management?

Q. What is the main goal of risk management?

Q. What is the risk exposure of a risk?