Question

How does the degree of control in a software development project increase?

a.

By increasing the number of control variables

b.

By increasing the degree to which the control variables can be varied

c.

By increasing the control variety

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:The degree to which a software development project can be controlled increases as the control variety increases. Control variety is determined by the number of control variables and the degree to which they can be varied.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How does the degree of control in a software development project increase?

Similar Questions

Discover Related MCQs

Q. What is necessary to measure both the project and the product in software development?

Q. What does controlling software development imply?

Q. How is controlling a software development project described in practice?

Q. What are the three classes of project characteristics that are important for project control?

Q. How does the degree of certainty of product characteristics affect project control?

Q. Which project characteristics are important for project control in software development?

Q. How does control differ in projects with high product certainty compared to low product certainty?

Q. What are the characteristics that are common to most or all software development projects?

Q. What are the three dimensions along which software development projects may differ?

Q. What factors determine the degree of product certainty in software development projects?

Q. What factors determine the degree of process certainty in software development projects?

Q. What is the primary determinant of resource certainty in software development projects?

Q. What are the aspects that will be discussed when discussing the control situations in software development projects?

Q. How many control situations can be derived from the three dimensions of product certainty, process certainty and resource certainty?

Q. What is the main emphasis in a situation where the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What type of process model may be used in a situation where the requirements are known and stable?

Q. What is the preferred method of coordination in a situation where the requirements are known and stable?

Q. How can cost estimation be done in a situation where the requirements are known and stable?

Q. What is the main emphasis when the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What is the main problem when there is uncertainty as regards resources?