Question

How does the degree of certainty of product characteristics affect project control?

a.

If product certainty is high, control can be quite rational, and compliance with requirements can be checked and corrective actions can be executed if needed.

b.

If product certainty is low, control will be different, as it is not feasible to check compliance with requirements or execute corrective actions.

c.

If product certainty is high, control will be different, as it is not feasible to check compliance with requirements or execute corrective actions.

d.

If product certainty is low, control can be quite rational, and compliance with requirements can be checked and corrective actions can be executed if needed.

Answer: (a).If product certainty is high, control can be quite rational, and compliance with requirements can be checked and corrective actions can be executed if needed. Explanation:If product certainty is high, control can be quite rational, as it depends on product characteristics and compliance with requirements can be checked and corrective actions can be executed if needed. However, if product certainty is low, it is not feasible to check compliance with requirements or execute corrective actions.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How does the degree of certainty of product characteristics affect project control?

Similar Questions

Discover Related MCQs

Q. Which project characteristics are important for project control in software development?

Q. How does control differ in projects with high product certainty compared to low product certainty?

Q. What are the characteristics that are common to most or all software development projects?

Q. What are the three dimensions along which software development projects may differ?

Q. What factors determine the degree of product certainty in software development projects?

Q. What factors determine the degree of process certainty in software development projects?

Q. What is the primary determinant of resource certainty in software development projects?

Q. What are the aspects that will be discussed when discussing the control situations in software development projects?

Q. How many control situations can be derived from the three dimensions of product certainty, process certainty and resource certainty?

Q. What is the main emphasis in a situation where the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What type of process model may be used in a situation where the requirements are known and stable?

Q. What is the preferred method of coordination in a situation where the requirements are known and stable?

Q. How can cost estimation be done in a situation where the requirements are known and stable?

Q. What is the main emphasis when the requirements are known and stable, and there is sufficient control variety and resources available?

Q. What is the main problem when there is uncertainty as regards resources?

Q. How can activities be coordinated in a project where there is uncertainty about resources?

Q. What development strategy can be used when there is uncertainty about resources?

Q. What is the primary problem in a situation where requirements are known and stable, but there is uncertainty regarding resources?

Q. What is the main problem in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?

Q. What is the recommended approach for controlling a project in a situation where the requirements are fixed and stable, but there is uncertainty regarding the process and resources?