What is the potential effect of experience on cost estimates in software development projects?

a.

Experience leads to more accurate and optimistic cost estimates

b.

Experience leads to more accurate and pessimistic cost estimates

c.

Experience leads to less accurate and pessimistic cost estimates

d.

Experience leads to higher productivity for subsequent projects

Posted under Software Engineering

Answer: (c).Experience leads to less accurate and pessimistic cost estimates Explanation:For lack of hard data, the cost of a software development project is often estimated through a comparison with earlier projects. If the estimator is very experienced, reasonable cost estimates may result. However, the learning effect of earlier experiences may lead to estimates that are too pessimistic in this case.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the potential effect of experience on cost estimates in software development projects?

Similar Questions

Discover Related MCQs

Q. What is the result of combining sufficiently different estimation methods?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?

Q. What is the main issue with using the comparison method for cost estimation?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the impact of software on a project's estimated effort?

Q. What is the impact of training on software cost estimation?

Q. How do requirements set or proposed affect the cost estimate?

Q. Is it advisable to make a cost estimate if it is not needed?

Q. How does shortening the development time of a project affect the manpower required?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. How can the development time for a project be shortened?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. What is the relationship between the number of communication links and team size?

Q. What is the impact of shortening the development time on the project?

Q. What is the impact of adding manpower to a late project on its completion date?