Question

What is the impact of software on a project's estimated effort?

a.

It decreases the estimated effort

b.

It does not have any impact on the estimated effort

c.

It increases the estimated effort

d.

It is impossible to determine

Answer: (c).It increases the estimated effort Explanation:Software has the tendency to grow, and projects have the tendency to far exceed the estimated effort." This implies that the estimated effort for a project is likely to be higher than initially thought due to the complexity and growth of software.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the impact of software on a project's estimated effort?

Similar Questions

Discover Related MCQs

Q. What is the impact of training on software cost estimation?

Q. How do requirements set or proposed affect the cost estimate?

Q. Is it advisable to make a cost estimate if it is not needed?

Q. How does shortening the development time of a project affect the manpower required?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. How can the development time for a project be shortened?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. What is the relationship between the number of communication links and team size?

Q. What is the impact of shortening the development time on the project?

Q. What is the impact of adding manpower to a late project on its completion date?

Q. What is the relationship between average productivity and average team size according to Conte et al. (1986)?

Q. What is the maximum limit of shortening a software development project according to Boehm?

Q. What is the relation between average productivity and average team size according to Conte et al.

Q. What is the maximum deviation from the actual cost that can be expected from an algorithmic cost estimation model like COCOMO 2?

Q. What is the impact of compressing the development time on cost according to the given information?

Q. What is the purpose of applying statistical techniques like regression analysis to a given set of project data in algorithmic models?

Q. What is a trade-off problem when it comes to software cost estimation?