How is the adjusted function point measure obtained in the FPA model?

a.

FP=UFP x TCF

b.

FP=UFP + TCF

c.

FP=UFP/TCF

d.

FP=UFP-TCF

Posted under Software Engineering

Answer: (a).FP=UFP x TCF Explanation:The (adjusted) function point measure FP is obtained through FP=UFP x TCF.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is the adjusted function point measure obtained in the FPA model?

Similar Questions

Discover Related MCQs

Q. How does the IFPUG help with counting function points in a uniform way in FPA?

Q. What are some of the problems with FPA's handling of complexity?

Q. How is the degree of influence of each characteristic in the FPA model valued?

Q. What is the main purpose of COCOMO 2?

Q. What are the three models provided by COCOMO 2?

Q. What is the basis of the Application Composition model in COCOMO 2?

Q. What is the main difference between Function Points used in FPA and Object Points used in the Application Composition model of COCOMO 2?

Q. What is the main advantage of Object Points over Function Points?

Q. What is the main use of the Application Composition model in COCOMO 2?

Q. How is the complexity level of each screen and report determined in the Application Composition model?

Q. How is the total effort estimated in the Application Composition model?

Q. How is the reuse percentage determined in the Application Composition model?

Q. What is the productivity rate used in the Application Composition model?

Q. What is the main purpose of the Application Composition model in COCOMO 2?

Q. How are Object Points determined in the Application Composition model?

Q. How is the number of function points determined in the Early Design model?

Q. What is the main difference between the Application Composition model and the Early Design model in COCOMO 2?

Q. What is the main advantage of using Object Points in the Application Composition model?

Q. How is the total effort in the Application Composition model estimated?

Q. How does the Post-Architecture model differ from the original COCOMO model?