adplus-dvertising
frame-decoration

Question

What is the maximum deviation from the actual cost that can be expected from an algorithmic cost estimation model like COCOMO 2?

a.

25%

b.

50%

c.

75%

d.

100%

Answer: (c).75% Explanation:Present-day models like COCOMO 2 yield estimates which are at most 25% off, 75% of the time, for projects used to derive the model.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the maximum deviation from the actual cost that can be expected from an algorithmic cost estimation model like COCOMO 2?

Similar Questions

Discover Related MCQs

Q. What is the relation between average productivity and average team size according to Conte et al.

Q. What is the maximum limit of shortening a software development project according to Boehm?

Q. What is the relationship between average productivity and average team size according to Conte et al. (1986)?

Q. What is the impact of adding manpower to a late project on its completion date?

Q. What is the impact of shortening the development time on the project?

Q. What is the relationship between the number of communication links and team size?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. How can the development time for a project be shortened?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. How does shortening the development time of a project affect the manpower required?

Q. Is it advisable to make a cost estimate if it is not needed?

Q. How do requirements set or proposed affect the cost estimate?

Q. What is the impact of training on software cost estimation?

Q. What is the impact of software on a project's estimated effort?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the main issue with using the comparison method for cost estimation?