What is the impact of shortening the development time on the project?

a.

It decreases the maximum workforce

b.

It decreases the initial slope of the Rayleigh curve

c.

It increases the maximum workforce

d.

It increases the initial slope of the Rayleigh curve

Answer: (d).It increases the initial slope of the Rayleigh curve Explanation:Shortening the development time amounts to an increase of the value 'a', the speed-up factor which determines the initial slope of the Rayleigh curve. This causes a faster increase of manpower required at the start of the project and a higher maximum workforce.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the impact of shortening the development time on the project?

Similar Questions

Discover Related MCQs

Q. What is the relationship between the number of communication links and team size?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. How can the development time for a project be shortened?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. How does shortening the development time of a project affect the manpower required?

Q. Is it advisable to make a cost estimate if it is not needed?

Q. How do requirements set or proposed affect the cost estimate?

Q. What is the impact of training on software cost estimation?

Q. What is the impact of software on a project's estimated effort?

Q. What is the expected effort using the technique of asking for three estimates?

Q. What is the recommended method to get a more reliable estimate?

Q. What is the impact of a compressed schedule on a software development project?

Q. What is the main issue with using the comparison method for cost estimation?

Q. What is the method that aims to get a more reliable estimate by having the expert produce more than one estimate?

Q. Why may estimates that are based on comparison with earlier projects be too pessimistic?

Q. What is the result of combining sufficiently different estimation methods?

Q. What is the potential effect of experience on cost estimates in software development projects?

Q. What is the best practice for improving estimates according to Lederer and Prasad (2000)?