Question

Is it advisable to make a cost estimate if it is not needed?

a.

Yes, it is advisable to make a cost estimate even if it is not needed

b.

No, it is not advisable to make a cost estimate if it is not needed

c.

Yer or No

d.

May be Yes or No

Posted under Software Engineering

Answer: (b).No, it is not advisable to make a cost estimate if it is not needed Explanation:If a cost estimate is not needed, it is wise not making one either.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Is it advisable to make a cost estimate if it is not needed?

Similar Questions

Discover Related MCQs

Q. How does shortening the development time of a project affect the manpower required?

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. How can the development time for a project be shortened?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. What is the relationship between the number of communication links and team size?

Q. What is the impact of shortening the development time on the project?

Q. What is the impact of adding manpower to a late project on its completion date?

Q. What is the relationship between average productivity and average team size according to Conte et al. (1986)?

Q. What is the maximum limit of shortening a software development project according to Boehm?

Q. What is the relation between average productivity and average team size according to Conte et al.

Q. What is the maximum deviation from the actual cost that can be expected from an algorithmic cost estimation model like COCOMO 2?

Q. What is the impact of compressing the development time on cost according to the given information?

Q. What is the purpose of applying statistical techniques like regression analysis to a given set of project data in algorithmic models?

Q. What is a trade-off problem when it comes to software cost estimation?