adplus-dvertising
frame-decoration

Question

What is the impact of an inexperienced software cost estimator on a project's estimated effort?

a.

It decreases the estimated effort

b.

It increases the estimated effort

c.

It does not have an impact on the estimated effort

d.

It is not specified

Posted under Software Engineering

Answer: (b).It increases the estimated effort Explanation:Studies in other fields show that inexperienced people tend to overestimate their abilities and performance. It is suggested that the same is true for people estimating software cost, leading to cost and schedule overruns.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the impact of an inexperienced software cost estimator on a project's estimated effort?

Similar Questions

Discover Related MCQs

Q. What does the Rayleigh curve model show when it comes to estimating development time for a project?

Q. How can the development time for a project be shortened?

Q. According to Brooks' Law, what happens when manpower is added to a late project?

Q. What is the relationship between average productivity and average team size according to Conte et al.'s study?

Q. What is the relationship between the number of communication links and team size?

Q. What is the impact of shortening the development time on the project?

Q. What is the impact of adding manpower to a late project on its completion date?

Q. What is the relationship between average productivity and average team size according to Conte et al. (1986)?

Q. What is the maximum limit of shortening a software development project according to Boehm?

Q. What is the relation between average productivity and average team size according to Conte et al.

Q. What is the maximum deviation from the actual cost that can be expected from an algorithmic cost estimation model like COCOMO 2?

Q. What is the impact of compressing the development time on cost according to the given information?

Q. What is the purpose of applying statistical techniques like regression analysis to a given set of project data in algorithmic models?

Q. What is a trade-off problem when it comes to software cost estimation?