What might be required after the integration and testing phase, depending on the nature of the system?

a.

Product release to the customer.

b.

A new version of the product with a total redesign.

c.

Maintenance of the system.

d.

Certification by an outside authority.

Answer: (d).Certification by an outside authority. Explanation:Depending on the nature of the system, it might be necessary to certify the final system according to requirements imposed by some outside authority, such as an aircraft certification board.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What might be required after the integration and testing phase, depending on the nature of the system?

Similar Questions

Discover Related MCQs

Q. What does the maintenance activity involve in the software life cycle?

Q. What is the main purpose of validation and verification in the software life cycle?

Q. What is the distinction between validation and verification?

Q. What activities are involved in the software life cycle?

Q. What is the main purpose of architectural design in the software life cycle?

Q. Which activity in the software life cycle involves refining the component description provided by architectural design?

Q. What is the primary purpose of validation in the software life cycle?

Q. Which phase of the software life cycle involves correcting errors in the system after release and revising the system to satisfy new requirements?

Q. What is the main difference between a formal proof and a rigorous proof?

Q. What is the "formality gap" referred to in the context of validation proofs?

Q. What may dictate the extent of proofs carried out in a design project?

Q. Which type of proof is more commonly used for verification in software development?

Q. What does the "formality gap" imply for the validation of interactive systems?

Q. How can the confidence in subjective proof be increased during validation?

Q. What is the importance of design notations in narrowing the formality gap for validation?

Q. In the context of software development, why are managerial issues of design important?

Q. What is the distinction between the technical perspective and the managerial perspective of the software life cycle?

Q. What does signing off on a requirements specification indicate?

Q. Why is it worth the effort to understand and improve the interactive system design process?

Q. Why is it challenging to determine all the requirements for an interactive system from the start?